TIMELINE EVENT
WSP approves revised Picacho demolition methods
What happened
Imperial County’s Public Works report says design engineer WSP approved revised demolition methods on Nov. 24, 2025, and the plans were sent to the Bureau of Reclamation.
- Event date
Sources 1
- Primary source · OtherImperial County Public Works Picacho Road Bridge report, Item 38 (Oct. 20, 2026)
Imperial County Public Works' staff report in the Oct. 20 Board agenda, Item 38. It records the partial-demolition and Reclamation-review chronology and reports the design engineer's Sept. 30 finding that current data indicates Picacho cannot be repaired and can only be replaced. The same report says final certification of the bridge condition is still being completed. The appended resolution has blank adoption fields and does not establish the Board's vote.
Related articles 1
- ExplainerWhy has the Picacho bridge been closed for 19 months? Imperial County's paperwork tells the story.
A guardrail crash, a federal canal, a shortage of floating platforms, a concrete curb in the water and, finally, an engineer’s finding that the bridge probably can’t be saved. Here’s how a closure “until further notice” turned into a year and a half.
Related topics 1
- Winterhaven's Bridges: Picacho, Arnold Road and the Quechan Nation
The Picacho Road Bridge into the Fort Yuma Quechan Reservation has been closed since March 2025, and the only detour crosses a bridge Imperial County has declared an emergency. We're following the records, the Tribe's requests and what the county does next.