County statement reports October 16, 2024 construction/payment injunction in Gila Electronics procurement litigation.
- Source type
- Government record
- Source classification
- Primary source
- Source date
- Not established in the reviewed record
Relevant excerpt / notes
County says injunction halted Master Agreement work/payments and expressly excluded operations/maintenance of operational portions. County identifies January 26, 2022 ALLO Master Agreement award. Later order and current case disposition not obtained; draft does not imply 2024 injunction remains in force or wrongdoing was adjudicated.
Related articles 1
- NewsYuma County reports 23 farm towers built; service still needs fiber and power
The County reports one middle-mile phase complete and two at 96% and 95%. Its farm broadband build has 23 towers substantially complete, but fiber, electricity and funding for 11 more towers remain unresolved.