Public Board packet containing eX2 Technology amendment, revised designs, costs and conditional deadline.
- Source type
- Contract
- Source classification
- Primary source
- Source date
- Not established in the reviewed record
Relevant excerpt / notes
Pages 6–10: original award December 2, 2024 for $3,775,135; contract entered December 19. Revised design requirements from APS, Wellton-Mohawk and FEMA; expansion 27 to 34 towers. First Amendment specifies $1,684,849.45 increase to $5,459,984.45 and August 31, 2026 completion contingent on state grant extension. Recitals supersede earlier changes described as potentially unauthorized. Public attachment is not an executed contract copy; later amendments and closeout not obtained.
Related articles 1
- NewsYuma County reports 23 farm towers built; service still needs fiber and power
The County reports one middle-mile phase complete and two at 96% and 95%. Its farm broadband build has 23 towers substantially complete, but fiber, electricity and funding for 11 more towers remain unresolved.