OTHER
Water Distribution Line 5th Street, Gila Street to Redondo: archived bid listing
About this source
Archived procurement listing summarizing the RFB-25-283 scope.
- Source type
- Other
- Source classification
- Secondary source / research lead
- Source date
Relevant excerpt / notes
Describes installation of a 30-inch PVC main and says the existing 20-inch main was undersized for current demand. This is a secondary archived listing, not the City's underlying bid documents; use only with attribution and qualify the need rationale as not stated in the council reports.
Related articles 1
- NewsYuma council approves second water-line change, lifting Gila-Redondo contract 19.8%
Yuma City Council approved a $99,763.07 second change order after crews found an existing water main beneath Redondo Center Drive, not west of the road as the plans showed. The two changes lift the Taylor Engineering contract from $1.38 million to $1.65 million; payment totals and the staff authorization record are not in the public documents reviewed.