City of Yuma Road Report, June 3, 2026
About this source
City notice of the water-line construction schedule and traffic impacts.
- Source type
- Government record
- Source classification
- Primary source
- Source date
Relevant excerpt / notes
Says work was to begin June 8, installing a water distribution line from 5th Street and Gila Street to Redondo Center Drive, with Redondo Center Drive closure and anticipated late-June completion. This was an advance estimate, not proof of actual completion date.
Related articles 1
- NewsYuma council approves second water-line change, lifting Gila-Redondo contract 19.8%
Yuma City Council approved a $99,763.07 second change order after crews found an existing water main beneath Redondo Center Drive, not west of the road as the plans showed. The two changes lift the Taylor Engineering contract from $1.38 million to $1.65 million; payment totals and the staff authorization record are not in the public documents reviewed.