Work-session minutes state Mayor Nicholls identified his firm's involvement as performing design for the project. Do not infer the firm supplied the specific utility-location information involved in the later discrepancy.
Related articles 1
- NewsYuma council approves second water-line change, lifting Gila-Redondo contract 19.8%
Yuma City Council approved a $99,763.07 second change order after crews found an existing water main beneath Redondo Center Drive, not west of the road as the plans showed. The two changes lift the Taylor Engineering contract from $1.38 million to $1.65 million; payment totals and the staff authorization record are not in the public documents reviewed.