GOVERNMENT RECORD
City of Yuma Council report MC 2026-185: Water-Line Change Order No. 2
About this source
City Council report and Legistar action record on the second change order for the 5th Street water distribution line project.
- Source type
- Government record
- Source classification
- Primary source
- Source date
- Not established in the reviewed record
Related articles 1
- NewsYuma water-line contract climbs nearly 20% after construction surprises
Yuma City Council approved a $99,763.07 second change order after crews found an existing water main beneath Redondo Center Drive, not west of the road as the plans showed. The two changes lift the Taylor Engineering contract from $1.38 million to $1.65 million; payment totals and the staff authorization record are not in the public documents reviewed.