GOVERNMENT RECORD
City of Yuma Council report MC 2026-105: First water-line change order
About this source
Council report and final action for the first change order on the 5th Street Gila-to-Redondo water line project.
- Source type
- Government record
- Source classification
- Primary source
- Source date
Relevant excerpt / notes
Council approved $173,229.66 on June 17. City reported an unexpected obstruction under Union Pacific Railroad right-of-way during jack-and-bore work, requiring UPRR/RailPros coordination, safety changes and removal; staff estimated two weeks added to schedule. The record calls for ratification and does not attach the underlying order or payment ledger.
Related articles 1
- NewsYuma water-line contract climbs nearly 20% after construction surprises
Yuma City Council approved a $99,763.07 second change order after crews found an existing water main beneath Redondo Center Drive, not west of the road as the plans showed. The two changes lift the Taylor Engineering contract from $1.38 million to $1.65 million; payment totals and the staff authorization record are not in the public documents reviewed.