YUMA, ARIZONAYuma news. Local context. Evidence you can check.

OTHER

City of San Luis

Updated

About this organization

The Arizona city where the project is located.

Sources 3

  • Primary source · ContractCity of San Luis contract: Cesar Chavez Boulevard Water Improvements (November 2024)

    Contract between the City of San Luis and Gutierrez Canales Engineering, PC, for $942,054.30 in water improvements along Cesar Chavez Blvd. Lists Tomas Sanchez, PE, RLS, of Core Engineering Group, PLLC, as project engineer/designer.

  • Primary source · Public statementCity of San Luis: ADOT approves Cesar Chavez Boulevard expansion

    Original City of San Luis announcement posted December 23, 2025, stating the project was awarded to DPE Construction. Automated retrieval returned HTTP 502 on November 6, 2026; this access failure does not establish that the original page is removed. See the separately linked October 30, 2026 City project update for later construction status.

  • Primary source · Public statementCity of San Luis: Cesar Chavez Boulevard project update, Oct. 30, 2026

    Official City of San Luis traffic and construction update. It identifies DPE Construction, Inc. as performing work at Cesar Chavez Boulevard and 7th Avenue as part of the Cesar Chavez Boulevard Widening - ADOT Project. This is later project-status evidence, not the contract award record.