Yuma Clears Temple Site Work; Building Permits Remain Pending

Yuma issued grading, plumbing and stormwater permits October 7 for the temple site. Building applications remain pending, and a work start is unverified.

Founder & Publisher

Updated
Architectural rendering of the proposed Yuma Arizona Temple, showing its central tower, arched entrance and desert landscaping.
An architectural rendering of the proposed Yuma Arizona Temple at East 36th Street and South Avenue 8E. The city has approved preliminary site work, while construction permits for the temple building remain pending. Credit: The Church of Jesus Christ of Latter-day Saints / Intellectual Reserve, Inc.
Published

Full article

The City of Yuma has issued permits for grading and utility preparation at the proposed Yuma Arizona Temple site, allowing the project to move into preliminary ground work while applications for the temple and its ancillary building remain unresolved.

City records checked October 12 show three permits issued October 7 for the property at 8045 E. 36th Street, near South Avenue 8E. They cover commercial grading and utilities, plumbing and stormwater pollution prevention. They do not establish that construction of the main temple has begun.

The Church of Jesus Christ of Latter-day Saints said in its October 5 announcement that city approvals would allow land grading and underground water, sewer and electrical connections. It said design work continued and no official groundbreaking date had been announced. The city portal separately records the permits' October 7 issuance.

What the city has cleared

The principal site-work permit, CSIT-104475-2026, was submitted July 20. Its description identifies grading and utility preparation for a new religious building. The workflow records a passed plan review September 10 and approved plans September 15.

The related permits are CPLB-105269-2026 for plumbing and SWPP-105263-2026 for stormwater. All three display an April 13, 2027 expiration date. That is a permit deadline, not a promised construction completion date.

Grading means shaping the ground before later construction. Underground utility work prepares service connections. A stormwater pollution prevention plan, commonly shortened to SWPPP, addresses pollution controls, inspections and corrective actions during construction. The public summaries do not establish the temple's specific drainage design or its effects on neighboring properties.

The grading permit lists Gutierrez Canales Engineering PC, doing business as GCE, under “Contractor,” Barton Architecture PLLC as an agent and Courtney Barton as architect. It records a $4.5 million valuation. That field is not a verified total temple budget, and the same figure repeated on the plumbing and stormwater permits should not be added together.

The buildings still need approval

The main religious-building application, COMB-105223-2026, was filed September 10 and remained “Under Review” on October 12, with no issue date. It explicitly refers to the separate grading and utilities permit.

The ancillary grounds-building application, COMB-105332-2026, was filed September 18. Its status was “Admin Failed,” and its workflow showed an initial administrative review not passed September 24. The public status does not explain the problem or establish a final denial. It also showed no permit issue date.

Yuma's Building Safety Division, within Community Development, handles building permits and inspections. The city says permits must be issued before construction. The main-building workflow lists electrical, mechanical, plumbing, fire-alarm and sprinkler subpermits among the remaining steps. Inspections and a certificate of occupancy are required before a completed building can be occupied.

What residents can expect next

The announced next phase is earthwork and underground connections. Whether crews had actually started by October 12 could not be independently confirmed. The grading permit's existing-inspections tab displayed no records, which leaves the start date unresolved rather than proving the site is inactive.

Earlier city records describe an Oriole Drive extension serving a future LDS church and future subdivisions, including water, sewer and roadway work. Those permits date to 2024 and are separate from the current site-work permits. They do not establish the temple's final entrances or a new road-closure schedule.

Detailed review information was restricted to record contacts. The publicly accessible material reviewed did not establish water or sewer capacity requirements, electrical-system changes, a traffic-impact finding, construction dates or neighborhood drainage effects.

The project was announced April 7, 2024. City records show a related lot split completed July 29, 2024, and a temple pre-development meeting held December 17, 2025. The Church released its location and rendering November 24, 2025, describing nearly seven acres, a single-story temple of about 18,500 square feet and an ancillary building.

A Latter-day Saint temple differs from a regular meetinghouse, where anyone may attend Sunday services. Temples are used for religious ceremonies, including marriages and family sealings. After dedication, entry is limited to members who meet the Church's requirements.