Somerton's Main Street closes on and off again until Nov. 25. It should be fully open by Dec. 5.

Starting Thursday, the stretch of U.S. 95 through downtown Somerton closes on and off again while crews put up archway steel. It's set to reopen for Thanksgiving weekend, then get its final paving.

Founder & Publisher

Updated
Orange editorial graphic of a road beneath an arch, with a traffic cone and calendar icon, announcing Main Street closures in Somerton.
Credit: Original Yuma Informed text graphic
Published

Full article

If you drive between Yuma and San Luis, you know Main Street in Somerton. It's U.S. 95, right through the middle of downtown.

Starting Thursday, it's closing again.

KAWC reported Tuesday that the street will be closed off and on over the next three weeks, between Somerton Avenue and the Regional Center for Border Health clinic. A delay in materials pushed the schedule back.

Here's the schedule, as KAWC reported it:

  • Thursday, Nov. 19, through Nov. 25: Crews install steel for the archway, with temporary closures.
  • Nov. 25: The street reopens for Thanksgiving weekend, once the steel work is done.
  • Starting Nov. 30: The final three-inch layer of asphalt goes down, plus signs and striping.
  • By Dec. 5: Main Street reopens once striping and signs are finished. That's the target, and it depends on the work getting done.

That leaves two weeks before the Tamale Festival on Dec. 19.

This is the city's Downtown Redevelopment Project, listed in public bid records as Main Street Improvements Phase 1. Earlier this year, repaving closed part of the street for months. Some downtown business owners told KAWC in June that the detour kept customers away.

What we don't know yet

  • Detours. KAWC didn't list them, and I couldn't find a city notice or map.
  • The city's own announcement. I looked and couldn't find one. Every date above is KAWC's report of the city's schedule.
  • What the project costs, and who's building it. You may see a dollar figure floating around online. I couldn't trace it to any record, so I'm not using it.

Where this comes from

  • KAWC, "Main Street in Somerton to close again for redevelopment project," Victor Calderón, Nov. 17, 2026. Reporting. Source for all dates, the closure limits and the materials delay. KAWC
  • KAWC, "Somerton downtown redevelopment project impacts some small businesses," June 30, 2026. Reporting. KAWC
  • Downtown Redevelopment Project, Main Street Improvements 2026 Phase 1, bid listing. Project record via ConstructConnect. ConstructConnect