Update
The Avenue 2E data facility is Gila Electronics. The county packet adds details, and a cooling-system question.
Gila Electronics proposes a 30,000-square-foot building with two technology pods south of Yuma. County staff recommends approval with conditions, but says the submitted equipment literature does not independently establish the cooling claims.
Founder & Publisher

- Published
Full article
The company behind the proposed communications and data processing facility on Avenue 2E is Gila Electronics. There is now considerably more to read than the legal notice.
The county's Nov. 24 hearing packet includes a staff report, site plans, the company's explanation and a letter from owner Harold Hendrick challenging several proposed conditions. It also raises a question the original notice could not answer: what, exactly, will cool the equipment?
Our Nov. 10 story covered the records then available. This is a new look at what the county has since posted.
A local company's proposed move
The applicant's narrative identifies Hendrick as the property owner and Gila Electronics of Yuma, Inc. as the proposed operator at 14255 S. Avenue 2E. It describes relocating and consolidating some of the company's existing communications, network and storage operations.
In his Nov. 11 letter, Hendrick describes a proposed 30,000-square-foot building for network equipment, limited office space, warehousing and contractor operations. He says the project is not an AI training facility or a hyperscale data center. That is the applicant's description of the proposal.
The company says it intends to start with two modular technology pods inside the warehouse for computing, network processing and data storage. Its narrative puts each pod at approximately 720 square feet.
The water claim has a qualification now
Gila's narrative says each pod would hold approximately 40 gallons of coolant in a closed-loop system, with no cooling towers, evaporative cooling or continuous cooling-water supply. It says a contractor would periodically remove and replace the coolant and take it off-site. The company expects the whole facility to use less water than a typical household.
Those remain the company's claims. The staff report adds an important limit: the manufacturer literature submitted with the application covers multiple cooling arrangements. It does not identify the specific equipment and configuration proposed here or independently substantiate the stated quantities and operating requirements.
Staff proposes requiring manufacturer specifications and a project-specific cooling design within two years of approval or before building permits, whichever comes first. The design would have to identify the coolant source and how the system gets rid of heat.
Hendrick's response says an independent engineer is developing the system. He asks the county to apply adopted technical standards and revise the proposed condition. The packet therefore contains both a low-water proposal and a clear statement that the specific design still needs documentation.
What staff recommends
County planners recommend approval of both the rezoning and special use permit, subject to conditions. That is a recommendation ahead of the hearing, not an approval.
The proposed conditions include a traffic impact analysis, daytime testing and maintenance of backup generators, and restrictions on generator use during normal operations. Staff also proposes keeping all data-processing pods inside the building, requiring separate approval for a battery energy storage system and limiting the special use permit to ten years.
Hendrick objects to several conditions in his letter, including the ten-year expiration, the battery-system restriction and the scope of fencing and future-building requirements. He asks for revisions. Those are positions for the county to consider, not findings that the conditions are unlawful.
Two requests on ten acres
Rezoning Case 26-08 would change the parcel from Rural Area, 10-acre minimum, to Light Industrial, 5-acre minimum. Special Use Permit Case 26-09 concerns the communications and data-processing use. The agenda identifies J.P. Mahon as agent for Hendrick and parcel 747-01-003 as the site.
The rezoning report says public water and sanitation service are not available in the area and that development would need individual septic systems and water wells. That makes the cooling design and water-source documentation useful questions, even with the company's low-water proposal.
The packet does not settle the facility's total electricity demand or identify a final equipment configuration. A proposed condition governing generators also does not tell us the number, size or fuel use of any eventual generators.
The hearing
The posted agenda confirms the Planning and Zoning Commission hearing for Tuesday, Nov. 24, at 5 p.m. in the E.F. Sanguinetti Auditorium, 197 S. Main St. The meeting can also be viewed on county government Channel 77.
The commission makes a recommendation. The Board of Supervisors makes the final decision.
For another local project where the water figures matter, see our reporting on the cobalt plant near Tacna.
Where this comes from
- Yuma County Planning and Zoning Commission packet, Nov. 24, 2026. Official hearing record. Agenda on PDF pages 1-2; rezoning report on pages 18-21; special use staff report on pages 31-36; applicant narrative on pages 42-46; Hendrick's Nov. 11 response on pages 52-57. Applicant statements and staff conclusions are distinguished above. Full packet / County agenda page
- Our Nov. 10 report. Earlier notice-based coverage, linked above.
Sources 2
- Primary source · Government recordPublic Notices / Agendas | Yuma County
Supporting source for the November 17, 2026 article. Scope and limitations are explained in the article and linked original.
- Primary source · Government recordYuma County Planning and Zoning Commission agenda packet, November 24, 2026
Official November 24, 2026 hearing packet. Special use staff report on PDF pages 31-36, Gila Electronics narrative on pages 42-46, and applicant response on pages 52-57. Applicant claims and staff recommendations are distinct from final approval.
Related topics 2
- Data Centers in Yuma County
A continuing record of data-center interest, economic-development activity, infrastructure discussions, public meetings and government decisions involving Yuma County.
- Yuma Land Use and Development
Yuma annexation, zoning and development decisions, including infrastructure obligations and opportunities for public participation.